- News
- Books
Featured Books
- pcb007 Magazine
Latest Issues
Current IssueThe Growing Industry
In this issue of PCB007 Magazine, we talk with leading economic experts, advocacy specialists in Washington, D.C., and PCB company leadership to get a well-rounded picture of what’s happening in the industry today. Don’t miss it.
The Sustainability Issue
Sustainability is one of the most widely used terms in business today, especially for electronics and manufacturing but what does it mean to you? We explore the environmental, business, and economic impacts.
The Fabricator’s Guide to IPC APEX EXPO
This issue previews many of the important events taking place at this year's show and highlights some changes and opportunities. So, buckle up. We are counting down to IPC APEX EXPO 2024.
- Articles
Article Highlights
- Columns
Search Console
- Links
- Events
||| MENU - pcb007 Magazine
Breaking the Bottleneck: Electrical Test Cycle Time Reduction
November 3, 2015 | Todd Kolmodin, Gardien ServicesEstimated reading time: 1 minute
As with many manufacturing theatres, there is a stream of additive processes that combine to create the finished product. The manufacture of printed circuits is no different. From the conception of the design and issuance of the procurement document, dozens of processes must take place before the PCB is shipped for assembly. Each of these processes takes time and the additive result of all these steps results in the manufacturing cycle, or lead time. Almost always, the customer just wants to know the lead time, or "When do I get my boards?"
However, in the manufacturing process steps leading to the final shipped product, there are individual cycle times within each process. From imaging all the way through final packaging, each process is allotted a predetermined amount of time to complete a given piece or full production order. In a perfect world, all individual process steps or cycle times will be completed early or on-time with the result being on-time delivery (OTD).
But, let's face it, many times Murphy makes an appearance and cycle times may increase. If this happens early in the manufacturing cycle, then the predetermined, gauged cycle time for subsequent processes is out the window. The time for those processes is now compressed or disregarded entirely and the order becomes ASAP. Did the time it took to effectively process that part miraculously compress as well? No, it did not. Now this order is competing with other orders in the same process step that were originally on-time, causing them to delay and WIP (work in process) to climb, thus resulting in the dreaded bottleneck! This is a term that sends chills through production managers and sales forces alike.
With that said, how do we combat this scenario? We streamline the process step by fine-tuning the attributes within that process. The result is reduced or optimized cycle time. This can result in the process step having "sprint capacity" to combat Mr. Murphy when he decides to make a visit. (However, in reality, once production planning finds out the process has reduced its cycle time…well you know what happens.)
Since I'm focused on quality assurance and electrical testing (ET), we will look at this scenario in the electrical test theatre.
Editor's Note: This article originally appeared in the October 2015 issue of The PCB Magazine.
Suggested Items
Inkjet Solder Mask ‘Has Arrived’
04/10/2024 | Pete Starkey, I-Connect007I was delighted to be invited to attend an interactive webinar entitled “Solder Mask Coating Made Easy with Additive Manufacturing,” hosted by SUSS MicroTec Netherlands in Eindhoven. The webinar was introduced and moderated by André Bodegom, managing director at Adeon Technologies, and the speakers were Mariana Van Dam, senior product manager PCB imaging solutions at AGFA in Belgium; Ashley Steers, sales manager at Electra Polymers in the UK; and Dr. Luca Gautero, product manager at SUSS MicroTec Netherlands.
NetVia Group Acquires Direct Imaging from Mivatek
04/09/2024 | Miva TechnologiesMiva Technologies is pleased to announce NetVia Group, Irving, TX has acquired a new Miva 2400NG Dual Tray Direct Imaging System with 30-micron capabilities for inner, outer and soldermask imaging.
Teledyne to Acquire Adimec
02/13/2024 | TeledyneTeledyne Technologies Incorporated announced that it has entered into an agreement to acquire Adimec Holding B.V. and its subsidiaries.
Real Time with... productronica 2023: MivaTek Global Advances Technology With High-res Imaging System
12/08/2023 | Real Time with...productronicaMivaTek's Brendan Hogan talks about how the company employs Digitally Adaptive Rasterization Technology (DART) in their high-res imaging equipment. He also shares how the blurred line between semiconductors and microelectronics is driving broader application of the imaging process.
Keysight Enables Validation of Arbe 4D Imaging Radar Chipset
11/30/2023 | Keysight Technologies, Inc.Keysight Technologies, Inc. announces that Arbe has selected the E8719A Radar Target Solution (RTS) to test the Arbe 4D imaging radar chipset for automotive applications.