As part of a recent I-Connect007 supply chain survey, we found that RF laminate material can be very difficult to obtain. Rogers Corporation was named specifically in our survey as one supplier with a limited amount of material available. In fact, their delivery time was reported as being as high as 55 days for some materials at one point. In an industry where quick turnaround time is critical, this is one supply line that killed any hope of being quick.

Because Rogers was noted by name in our findings, we decided to go to them to learn about the current situation, and the short answer is that there has been improvement on delivery lead time with the promise of continued improvement.

The following interview is with John Pavlak, the director of global operations at Rogers Corporation.

Barry Matties: John, can you please give us an idea of what happened to your supply line and explain what you are doing to improve.

Pavlak: I can give you the story as I know it from my two years so far at Rogers. When I started in mid-2013, we had a plan to increase capacity because our market intelligence said that there was significant demand coming and it was primarily tied to the China 4G roll-out.

The only difference between our plan and what actually happened, the 4G roll-out actually came in sooner than our original marketing intelligence. Fortunately, we had already kicked off projects to increase our global capacity. The challenge was that those were long lead-time and very expensive projects. We’ve invested more than $30 million in the past three years into global capacity projects.

We had ourselves locked in tightly with different OEMs and fabricators, but the wave of demand came sooner than expected, so we spent the latter half of 2013, and almost all of 2014, working very hard to increase capacity in other ways before that additional capacity came online. Every one of our locations in the global regions added capacity through internal improvements on throughput and figured out how to get more lamination press loads per week. All of our teams pushed very hard and each of the regions were able to demonstrate at least another 20% of additional capacity, even without the new equipment.

Read the full article here.

 

Editor's Note: This article originally appeared in the July 2015 issue of The PCB Magazine.

Share

Print


Suggested Items

Rooting Out an 'Us vs. Them' Mentality: An Interview with Laura Kriska

04/02/2021 | Dan Beaulieu, D.B. Management Group
Earlier this year, I-Connect007 columnist Dan Beaulieu submitted a book review on "The Business of WE: The Proven Three-Step Process for Closing the Gap Between Us and Them in Your Workplace." As a follow up to that review, Dan has interviewed the book's author, Laura Kriska.

Millennials and Seasoned Veterans: Your Future Lies in Both

12/29/2020 | Dan Beaulieu, D.B. Management Group
There is no doubt that we are having a crisis when it comes to the workforce in our industry today. In the PCB and PCBA industries, as well as most manufacturing industries, there is a definite shortage of good people we can hire. Dan Beaulieu describes how the future of the electronics manufacturing industry lies in both millennials and seasoned veterans alike.

14 ‘Business as Usual’ Tips, Part 6

05/21/2020 | Dan Beaulieu, D.B. Management Group
In this series, Dan Beaulieu will share 14 “business as usual” tips for selling without visiting customers during the COVID-19 outbreak. In Part 6, he shares two tips for taking care of your mental health during these uncertain times.



Copyright © 2021 I-Connect007. All rights reserved.